DCVG Coating Defect Log

0 immediate/30-day · 6 planned · 4 monitor · severity per NACE SP0502
IndicationStructureKP %IRSeverityCategoryDescription
DC-2201 PL-06" SGPC–TIPU 12.40 34% Cat 3 — planned PL-06 KP12.4 holiday
DC-2202 PL-08" SUJAWAL Loop 03.85 28% Cat 3 — planned Girth-weld coating loss
DC-2203 PL-08" SUJAWAL Loop 07.10 26% Cat 3 — planned Disbonded tape wrap
DC-2204 PL-10" MARI–DAHARKI 38.10 22% Cat 3 — planned Rock damage, backfill
DC-2205 PL-04" TIPU Gathering 02.60 18% Cat 3 — planned Mechanical damage
DC-2206 PL-12" KANDHKOT Trunk 11.65 16% Cat 3 — planned Coating blister
DC-2207 PL-06" SGPC–TIPU 08.60 12% Cat 4 — monitor Minor holiday
DC-2208 PL-16" MARI Export 24.35 9% Cat 4 — monitor Pinhole, surface
DC-2209 ZS-Flowline Network 06.40 7% Cat 4 — monitor Minor holiday
DC-2210 PL-12" KANDHKOT Trunk 07.20 5% Cat 4 — monitor Surface scratch

%IR is the voltage-gradient drop across the defect as a percentage of pipe-to-remote-earth. Bands per NACE SP0502: Cat 1 ≥60% immediate · Cat 2 35–60% within 30 days · Cat 3 16–35% scheduled · Cat 4 <16% monitor. Severity is prioritised alongside the CP potential at that location, never on its own.