Week 25 — 15 to 21 June 2026

11 scheduled activities · intervals driven by 49 CFR 192.465, NACE SP0207/SP0502 and EN ISO 18086
Excavation window Thu–Fri · CA-1042
Mon15
07:30
DCVG survey — Z-01 KP 8.0–16.4

ECDA indirect inspection

A. Sattar + 2NACE SP0502
15:00
Rectifier check — TR-01, TR-04

Output, tap position, hours run

M. Iqbal192.465(a)
Tue16
09:00
CP performance meeting

KPI pack, overdue actions, budget

Management
13:00
DCVG data reduction

%IR calculation, defect classification

A. SattarNACE SP0502
Wed17
08:00
AC interference monitoring — Z-05

Coupon current density at HV crossing

K. NawazEN ISO 18086
14:30
Anomaly prioritisation

Rank digs by %IR against CP potential

CP cellSP0502 §5
Thu18
06:00
Excavation window — KP 12.4

Expose, clean, assess coating condition

ContractorCA-1042
11:00
Direct examination — KP 12.4

Pit depth, wall loss, photographic record

A. SattarSP0502 §6
Fri19
07:00
Recoat & backfill — KP 12.4

Apply repair coating, holiday-test, backfill

ContractorCA-1042
14:00
Rectifier commissioning — TR-14

New TR unit, set output, verify drain

M. IqbalCA-1041
Sat20
05:30
Depolarisation test — Z-02

4 h decay after interruption, 100 mV check

S. BhattiSP0169
Sun21
No scheduled activity
Rectifier check CIPS survey Test-post survey DCVG survey AC monitoring Depolarisation Excavation Verification Review Meeting

The week reads as one closed loop: survey (Mon) → classify (Tue–Wed) → excavate and repair (Thu–Fri) → verify by depolarisation (Sat). Rectifier checks sit on their own 2-month clock and cannot slip.