1Protection Status

classified on −850 mV instant-OFF · AMPP SP0169
Fully Protected

1,842

73.9% of 2,491 surveyed
Partially Protected

431

17.3% — some test points fail
Unprotected

218

8.8% — all readings fail
Not Yet Surveyed

570

no valid reading in 15 months

Protection State

Classified on −850 mV instant-OFF vs Cu/CuSO₄ (AMPP SP0169).

Are we winning? — 12-month trend

+6.1% fully protected YoY

2Inspection Plan vs Actual

intervals per 49 CFR 192.465

Annual Inspection Plan vs Actual

FY 2026 · 77.9% complete

Compliance Clock

Test posts — ≤ 15 months 94%
2,342 of 2,491 within interval
Rectifiers — ≤ 2 months 61%
47 rectifiers out of interval
CIPS coverage of pipeline km 72%
418 km of 581 km surveyed

Intervals per 49 CFR 192.465 — test stations annually (≤ 15 months); rectifiers 6×/year (≤ 2 months).

3Evidence — readings & system health

what puts each structure in its bucket

Potential Distribution — instant-OFF

criterion −850 mV

Criteria & System Health

−850 mV instant-OFF 1,842 pass 74%
−850 mV ON potential 2,106 pass 85%
100 mV polarisation 1,961 pass 79%
Rectifiers energised 132 of 141 9 down
Anode beds depleted < 20% life 14
DCVG coating defects 287 indications 31 severe
Interference / stray current sites identified 19

4Corrective Actions

immediate · short-term · long-term

Corrective Actions — closing the loop to Fully Protected

251 open

23

Immediate unprotected + severe defect

88

Short-term within this inspection cycle

140

Long-term capex / next budget cycle
StructureTypeInstant-OFF StateRoot causeCorrective actionHorizon
MPCL-SGPC-GRUB-WHS1Well casing −612 mV Unprotected Rectifier R-14 failed Replace rectifier transformer unit Immediate
PL-06″ SGPC–TIPU KP 12.4Pipeline −698 mV Unprotected DCVG severe holiday, 34% IR Excavate & recoat, then re-survey Immediate
TK-2201 Crude StorageTank base −806 mV Partial Anode bed 17% remaining Install supplementary deep anode bed Short-term
PL-10″ MARI–DAHARKI KP 38.1Pipeline −824 mV Partial Stray current from HT crossing Install drainage bond & monitor Short-term
ZS-Flowline Network (14 km)Flowline −831 mV Partial Insufficient current density CP redesign & upgrade groundbed Long-term
PL-08″ SUJAWAL LoopPipeline −744 mV Unprotected Coating degradation, 1998 asset Full recoat programme, phased Long-term